Oregon Inlet Clogged, Dredging in Limbo

Dredging crews are set to survey the Oregon Inlet again this morning after they suspended operations due to shallow waters. Officials with the U-S Army Corps of Engineers say strong winds brought more sand into the inlet last week. That prevents crews from using their side-casting dredge. Bob Sattin is the cheif operator for the Army Corps of Engineers in Wilmington:

"A side-casting dredge is a dredge that works almost like a lawnmower would work. As it goes over the material, it sucks it up, and then casts it out to the side of the channel. The side-caster needs 5.5 feet in depth of water in order to work. Right now, Oregon Inlet is two feet deep."

Sattin says the corps' does not have the estimated $17 million to contract an ocean pipeline dredge, which works in shallow water. Oregon Inlet serves as a link to the ocean for much of the commercial fishing industry in Croatan Sound.

  • Facebook
  • Twitter
  • LinkedIn
  • Email
Will Michaels is WUNC's Weekend Host and Reporter.
More Stories
  1. Dare County leaders support Oregon Inlet jetty
  2. Parts of Oregon Inlet too shallow for boats, but help is on the way
  3. State Officials Eye Harvest Restrictions To Rebuild Southern Flounder Stock
  4. How Did North Carolina's Commercial Fishing Industry Fare In Hurricane Florence?
  5. Coast Guard Warns Of Shipping Hazard From Containers Lost At Sea